Protection Standard (Procedure) under 2026

site-control (base, protection, traffic)

Standard procedure for implementing protection as part of work quality and credibility, on the premise that the site is borrowed space. For the notice, see [Notice] Protection Standard (2026).

Pre- and post-work check standards

1. Purpose

This procedure aims to standardize the implementation of protection on site based on the Protection Standard (2026).

"Protection" means measures to protect existing floors, walls, ceilings, equipment, fixtures and valuables from damage or soiling during construction, delivery or removal. We position protection as part of work quality and S-TEKT credibility and as fulfilling our responsibility to return borrowed space properly.

2. Principle

Omission or inadequate implementation of protection is prohibited.

Implement protection according to level (minor / normal / high-risk). Scope and procedure shall follow this procedure.

3. Protection Targets

Implement protection for the following as applicable.

TargetPurposeMain materials
FloorProtection of work area, bring-in route, standing areaProtection sheet, board
WallProtection of wall/surface near workProtection sheet, masking
CeilingProtection of ceiling when working on platform or on bring-in routeProtection sheet (as needed)
Equipment / fixturesContact prevention for existing equipment, fixtures, displaysProtection sheet, relocation
TrafficSecuring passage, emergency exit, boundary with other areasProtection, signage, barriers

4. Protection Level (Minor / Normal / High-Risk)

Determine level according to site conditions and meet the required items and records in the table below.

LevelCriteriaRequiredRecords
MinorFew targets, low soiling risk (person in charge decides)Minimum protection for bring-in route etc.Not required
NormalGeneral siteImplement floor, wall, route protection per procedureRecord recommended
High-riskHigh-value materials (glass, marble, mirror, etc.), displays, strong shared useDouble protection and confirmation by person in charge requiredPhoto record (Before/After) required

5. Pre-Implementation Confirmation

6. Protection Implementation Flow

Implement protection in the following order.

Confirm targets

Determine level

Prepare materials

Floor protection (route, work area)

Wall and equipment protection

Secure traffic and mark boundary

Person in charge confirmation (for high-risk)

Records

Prohibited

  • Direct application of protection tape to finished surfaces (causes damage or peeling when removed)
  • Insufficient protection area
  • Omitting protection on high-risk sites

7. Removal and Restoration

Principle: "Return in better condition than before installation."

Clean work area and remove waste

Remove protection sheets and boards (without spreading soiling)

Confirm finish

If abnormality: report and arrange repair

Complete

8. Records

Protection implementation records by level: